During a project retrospective, two lead engineers strongly disagree about which database platform to adopt. Rather than picking a side or splitting the difference, the project manager facilitates a working session where both engineers share their underlying requirements, and together the team designs a solution that satisfies both sets of concerns. Which conflict resolution technique is the project manager using?