Question 8 of 149
During planning for an office relocation project, a project manager has finalized cost estimates for every work package in the WBS. The manager now aggregates these package-level costs, adds the contingency reserve for identified risks, and produces a time-phased spending curve that will be used to measure cost performance during execution. What is the manager producing?