🔥 3-day streak
CompTIA Project+ (PK0-005)5 / 149
Question 5 of 149

During planning for a data center migration, the project manager identifies a high-probability, high-impact risk: performing the cutover during the company's peak sales season could cause catastrophic revenue loss if the migration fails. After discussion, the team decides to reschedule the entire cutover to occur after the sales season ends, eliminating any chance of this risk affecting the peak period. Which negative risk response strategy does this represent?