CompTIA Project+ (PK0-005)2 / 149
Question 2 of 149

A project manager has obtained the customer's formal sign-off on all deliverables, and the final invoice from the vendor has been paid and the contract formally closed. The project team is still assigned to the project, and internal records remain open in the PMO system. Which activity should the project manager perform NEXT to properly complete the project?