Question 1 of 149

During a weekly project meeting, a stakeholder raises an idea that is important but outside the current meeting's scope and unrelated to any immediate deliverable. The project manager wants to capture the idea so it is not lost but also keep the meeting on track. Which documentation approach should the project manager use for this idea?