CompTIA Project+ (PK0-005) · Difficulty

Medium PK0-005 practice questions

Applied — put a concept to work in a realistic situation. 133 medium questions available — no sign-up, always free.

Question 1 of 25

During a weekly project meeting, a stakeholder raises an idea that is important but outside the current meeting's scope and unrelated to any immediate deliverable. The project manager wants to capture the idea so it is not lost but also keep the meeting on track. Which documentation approach should the project manager use for this idea?

Reviewed for accuracy · Report an issue
Question 2 of 25

A project manager has obtained the customer's formal sign-off on all deliverables, and the final invoice from the vendor has been paid and the contract formally closed. The project team is still assigned to the project, and internal records remain open in the PMO system. Which activity should the project manager perform NEXT to properly complete the project?

Reviewed for accuracy · Report an issue
Question 3 of 25

A software team using Scrum is midway through a project. The project manager wants to forecast how much work the team can realistically complete in upcoming sprints so the sponsor can be given a credible delivery projection. Which metric should the project manager rely on for this forecast?

Reviewed for accuracy · Report an issue
Question 4 of 25

During planning for a new office relocation project, the project manager estimates the move will take one weekend based on the belief that the building's freight elevator will be available on Saturday and Sunday. The facilities team has not yet confirmed this. Where should the project manager record this belief so it can be tracked and validated later?

Reviewed for accuracy · Report an issue
Question 5 of 25

During planning for a data center migration, the project manager identifies a high-probability, high-impact risk: performing the cutover during the company's peak sales season could cause catastrophic revenue loss if the migration fails. After discussion, the team decides to reschedule the entire cutover to occur after the sales season ends, eliminating any chance of this risk affecting the peak period. Which negative risk response strategy does this represent?

Reviewed for accuracy · Report an issue
Question 6 of 25

A project manager is analyzing the schedule network diagram. An activity on a non-critical path has an early start of day 8 and a late start of day 12. The project sponsor asks how long this activity can be delayed without pushing back the project completion date. What is the correct answer?

Reviewed for accuracy · Report an issue
Question 7 of 25

A project team is releasing a major update to a customer-facing e-commerce application that must remain available 24/7. The operations manager wants the ability to switch users to the new version instantly and revert immediately if problems surface, with minimal risk to live traffic. Which deployment approach best meets these requirements?

Reviewed for accuracy · Report an issue
Question 8 of 25

During planning for an office relocation project, a project manager has finalized cost estimates for every work package in the WBS. The manager now aggregates these package-level costs, adds the contingency reserve for identified risks, and produces a time-phased spending curve that will be used to measure cost performance during execution. What is the manager producing?

Reviewed for accuracy · Report an issue
Question 9 of 25

During the discovery phase, an executive committee asks the project manager to provide a document that justifies the proposed project by comparing the expected costs, benefits, and return on investment against the organization's strategic goals. This document will be used to decide whether to fund the initiative. Which document should the project manager provide?

Reviewed for accuracy · Report an issue
Question 10 of 25

A project team is preparing to deploy a new customer billing module into the organization's production environment. The organization follows ITIL service management practices. Before the deployment can proceed, the operations group insists the change be formally reviewed for risk, scheduling conflicts with other releases, and potential business impact. Which governance body is responsible for authorizing this production change?

Reviewed for accuracy · Report an issue
Question 11 of 25

During execution of a predictive project, a stakeholder submits a formal request to add a new reporting feature that would increase both cost and schedule. The project manager has already logged the request. What should the project manager do NEXT before any work on the change begins?

Reviewed for accuracy · Report an issue
Question 12 of 25

During a project retrospective, two lead engineers strongly disagree about which database platform to adopt. Rather than picking a side or splitting the difference, the project manager facilitates a working session where both engineers share their underlying requirements, and together the team designs a solution that satisfies both sets of concerns. Which conflict resolution technique is the project manager using?

Reviewed for accuracy · Report an issue
Question 13 of 25

A project manager is assembling a team for a highly complex, time-sensitive product launch that will require constant collaboration and rapid problem-solving among developers, designers, and QA testers. The organization has office space available and asks the PM whether to place the team in one shared physical location or allow them to work independently from separate buildings. Which is the PRIMARY benefit the PM should cite in favor of a collocated team?

Reviewed for accuracy · Report an issue
Question 14 of 25

A project team currently has 6 members, all of whom communicate directly with one another. The sponsor authorizes adding 4 more team members to accelerate delivery. The project manager is concerned about the increased complexity of communication. Approximately how many total communication channels will exist after the new members join?

Reviewed for accuracy · Report an issue
Question 15 of 25

A vendor supporting your project has informed you verbally that they need to adjust a contractual deliverable date that will affect the project's legally binding agreement. As the project manager, you need to document this change and ensure both organizations have an official, authoritative record for potential future disputes. Which communication method is MOST appropriate?

Reviewed for accuracy · Report an issue
Question 16 of 25

Two functional managers on a project disagree over how a shared testing lab should be scheduled. Neither will get full access to the lab during the critical testing window. After discussion, the project manager helps them agree that each team gets the lab for half the available days, with both giving up some of what they originally wanted so the project can move forward. Which conflict resolution technique did the project manager use?

Reviewed for accuracy · Report an issue
Question 17 of 25

Two engineers on your project disagree about which database technology to use. Rather than picking a side quickly, you gather both engineers, review the performance requirements, benchmark data, and long-term maintenance costs together, then reach a decision supported by the evidence. Which conflict resolution technique are you using?

Reviewed for accuracy · Report an issue
Question 18 of 25

A project manager has received formal customer sign-off on all deliverables from an external vendor who supplied specialized equipment under a fixed-price contract. Before the project can be fully closed, the PM wants to ensure the procurement relationship is properly ended. Which action is MOST important to complete during contract closeout?

Reviewed for accuracy · Report an issue
Question 19 of 25

During the execution of a manufacturing project, the project manager receives a batch of 500 finished components from the production line. Before shipping them to the customer, she directs the team to measure a sample of the components against the documented dimensional tolerances to identify any defective units. Which activity is the project manager performing?

Reviewed for accuracy · Report an issue
Question 20 of 25

A project manager is halfway through the execution phase of a software rollout. During a status review, they compare the actual completion dates of tasks against the dates recorded when the schedule was approved by the sponsor. Several tasks are finishing later than originally documented. Which reference point is the project manager using to measure this timing discrepancy?

Reviewed for accuracy · Report an issue
Question 21 of 25

A steering committee is reviewing three proposed initiatives during the discovery phase. They want an objective way to compare each proposal by weighing the total anticipated financial returns against the estimated costs before deciding which one to authorize with a charter. Which tool should the project sponsor use to support this selection decision?

Reviewed for accuracy · Report an issue
Question 22 of 25

A project manager is reviewing earned value data at the end of month three. The earned value (EV) is $180,000 and the actual cost (AC) is $200,000. The sponsor asks whether the project is spending money efficiently relative to the work accomplished. Which calculation should the project manager present, and what does the result indicate?

Reviewed for accuracy · Report an issue
Question 23 of 25

A predictive software deployment project is running two weeks behind on a critical-path activity, and the delivery deadline cannot move because it is tied to a contractual milestone. The project manager has budget available and decides to add two experienced developers to the delayed task to bring it back on schedule. Which schedule compression technique is the project manager using?

Reviewed for accuracy · Report an issue
Question 24 of 25

A project manager is finalizing the schedule for a software rollout. The network diagram shows four possible paths from start to finish with the following total durations: Path 1 = 22 days, Path 2 = 30 days, Path 3 = 27 days, and Path 4 = 25 days. The sponsor asks the project manager which path the team must monitor most closely because any delay on it will directly push out the project completion date. Which path should the project manager identify?

Reviewed for accuracy · Report an issue
Question 25 of 25

You are managing a software project using an agile approach. Each morning the development team gathers for 15 minutes so each member states what they completed yesterday, what they will work on today, and any blockers preventing progress. Which purpose does this recurring meeting primarily serve?

Reviewed for accuracy · Report an issue