CompTIA Project+ (PK0-005) · Difficulty

Hard PK0-005 practice questions

Challenge — multi-step scenarios, trade-offs, and subtle distinctions. 10 hard questions available — no sign-up, always free.

Question 1 of 10

Halfway through a predictive project, the project manager reviews earned value data. The budget at completion (BAC) is $200,000. The earned value (EV) is $90,000, the actual cost (AC) is $110,000, and the planned value (PV) is $100,000. What does this data tell the project manager about the project's cost performance?

Reviewed for accuracy · Report an issue
Question 2 of 10

During quantitative risk analysis, a project manager evaluates two vendor options for a critical component. Vendor A has a 30% chance of a $50,000 delay cost and a 70% chance of no additional cost. Vendor B has a 10% chance of an $80,000 delay cost and a 90% chance of no additional cost. Which vendor should the project manager select based on expected monetary value (EMV)?

Reviewed for accuracy · Report an issue
Question 3 of 10

During a project, two senior engineers strongly disagree about whether to use a new database platform. The debate has stalled a critical safety-related deliverable, and a regulatory deadline is only two days away. The project manager has listened to both positions, but there is no time left for consensus. Which conflict resolution technique should the project manager apply?

Reviewed for accuracy · Report an issue
Question 4 of 10

During execution of a corporate relocation project, an unforeseen structural issue with the new building is discovered that was not identified in the risk register. Addressing it will require additional funds beyond the cost baseline and the contingency reserve. Which funding source should the project manager pursue, and who typically controls it?

Reviewed for accuracy · Report an issue
Question 5 of 10

A project manager is building the schedule for a network installation. Activity A (3 days) is followed by Activity B (5 days), which is followed by Activity D (2 days). A separate path runs Activity A, then Activity C (4 days), then Activity D. Using a forward pass starting at day 0, what is the earliest the project can finish?

Reviewed for accuracy · Report an issue
Question 6 of 10

During execution of a software migration project, the project manager identifies that a newly released cloud automation tool could dramatically reduce the deployment effort if adopted. The team confirms the benefit is significant, and the PM reassigns the most skilled engineers and adjusts the plan to ensure the project fully captures this benefit. Which risk response strategy is the project manager applying?

Reviewed for accuracy · Report an issue
Question 7 of 10

A project manager implements a risk response by outsourcing a specialized data migration to a third-party vendor to reduce the chance of technical failure. During planning, the team realizes that relying on the vendor introduces a new concern: the vendor may miss the delivery deadline, delaying the project. How should the project manager classify and handle this new concern?

Reviewed for accuracy · Report an issue
Question 8 of 10

During contract negotiations with a managed hosting vendor, the vendor proposes a clause allowing them to recover previously issued service credits if they maintain 100% uptime for three consecutive months following any breach. As the project manager reviewing the SLA, what does this clause represent, and what should you consider?

Reviewed for accuracy · Report an issue
Question 9 of 10

A project has consumed $400,000 of its $500,000 budget, but a recent market shift means the product will no longer meet customer needs and cannot be sold. Completing the remaining work will cost another $100,000, and the finished product is now expected to generate no revenue. Reworking the concept would require a new $250,000 project that is forecast to generate $600,000 in revenue. What should the project manager recommend to the sponsor?

Reviewed for accuracy · Report an issue
Question 10 of 10

A project manager is monitoring a software rollout that is currently over budget. The sponsor insists the project must still be completed within the original approved budget (BAC). To assess whether this is realistic, the project manager wants to calculate the cost efficiency the team must achieve on the remaining work to meet that budget target. Which metric should the project manager calculate?

Reviewed for accuracy · Report an issue