Question 42 of 139
A project manager asks Microsoft 365 Copilot: "Summarize the attached project status report." The result is a long, unstructured paragraph, but the manager actually needs a short list of key risks with an owner and due date for each, so it can be pasted into a status email. How should the manager revise the prompt to get a more useful result?