Question 121 of 186
A media company is closing an on-premises data center in 90 days. They must migrate 600 TB of archived video assets to Amazon S3. The site has a single 500 Mbps internet link that is already 60% utilized by production traffic, and the company cannot upgrade the connection before the deadline. After the initial bulk migration, a smaller pool of about 2 TB of newly created files per week must continue to be transferred to S3 until the data center is fully decommissioned. Which approach meets the timeline while minimizing risk and impact on production traffic?