A company must vacate its colocation data center in 90 days after a lease was not renewed. The environment contains roughly 250 physical and virtual servers running a mix of Windows and Linux workloads, including several tightly coupled legacy applications whose source code is unavailable. The team has no capacity to refactor or re-architect anything before the deadline, but they want automated, block-level replication with continuous data sync so that final cutover produces minimal downtime and a low RPO. Which approach best meets these requirements within the timeline?