Process
Drill 20 practice questions focused entirely on Process for the PMI PMP exam. Tap an answer for instant feedback and a full explanation — no sign-up, always free.
A project team is building a large customer-facing platform under a predictive plan that schedules a single go-live in 14 months. Midway through planning, the sponsor expresses concern that competitors are moving quickly and that the business will see no return until the entire platform launches. The sponsor asks the project manager how the team could begin realizing benefits sooner without abandoning the overall delivery commitment. What should the project manager do first?
A predictive project has just received formal acceptance of the final deliverable from the customer. The project used two external vendors under fixed-price contracts, and there are still open invoices and one unresolved claim with one vendor. The sponsor asks the project manager to close the project quickly so the team can be released. What should the project manager do FIRST?
During execution of a globally distributed hybrid project, the project manager discovers a critical technical defect that requires an immediate decision from the sponsor and two lead architects who are in different time zones. The next scheduled steering committee meeting is in five days, but the defect is blocking a release planned for tomorrow. What is the BEST communication approach for the project manager to take?
A project manager on a large infrastructure program sends a detailed weekly status report of 15 pages to all 40 stakeholders. Several executive sponsors complain that they do not have time to read the reports and are missing the key decisions that require their input, while some technical team leads say the report lacks the depth they need. What should the project manager do to improve communication effectiveness?
A project team has been experiencing a high rate of rejected deliverables during the quality control inspection stage, which occurs at the very end of each production cycle. The project manager notices that reworking these defects is consuming a large portion of the budget and delaying the schedule. The sponsor asks the project manager to reduce these quality-related costs. What is the BEST approach for the project manager to take?
A project manager is halfway through a predictive construction project. The performance report shows a budget at completion (BAC) of $500,000, earned value (EV) of $200,000, actual cost (AC) of $250,000, and planned value (PV) of $240,000. The sponsor asks the project manager to forecast the total cost the project will require at completion, assuming the current cost performance trend continues for the remainder of the work. What should the project manager report?
A project manager is developing the initial budget for a new product-development project during the early planning stage. Very little detailed design information is available, and the sponsor needs a rough order-of-magnitude cost figure quickly to decide whether to authorize the project. The PM has data from three similar past projects the organization completed. Which estimating approach should the PM use to produce this initial cost figure?
Midway through a predictive infrastructure project, several small problems have surfaced during status meetings: a delayed vendor shipment, an unresolved question about server naming conventions, and a team member's uncertainty about who approves environment access. The project manager notices these items keep resurfacing in meetings without resolution because there is no consistent way to track them. What should the project manager do to bring order to these situations?
A project manager is launching a large transformation program that spans three business units, each with its own director. Early in the project, decisions about scope trade-offs and budget reallocations are being made inconsistently, and some directors reverse choices made by others, causing rework. The project manager has a charter and a sponsor but no defined mechanism for cross-unit decisions. What should the project manager do FIRST to address this situation?
A project manager is leading a product development effort with two distinct parts: a hardware component that is subject to strict regulatory approvals with fixed compliance milestones, and a software component whose requirements are still evolving based on user feedback. The sponsor wants both parts delivered under one project and asks the PM to recommend how to structure the delivery approach. What should the PM recommend?
A software product team has a 12-month roadmap with dozens of planned features. The sponsor is under pressure from the executive board to show tangible business returns within the first quarter. The product owner and team estimate that the full solution cannot be completed for at least eight months. What should the project manager recommend to best deliver business value under these circumstances?
Midway through a 14-month predictive project, the project manager notices the team keeps encountering integration problems that a previous, similar project also faced. The organization has a lessons learned repository, but the current team has not consulted it since the project charter was approved. What should the project manager do to best ensure project continuity and avoid repeating past mistakes?
During integrated planning for a hybrid project, the project manager discovers that the schedule baseline assumes a vendor deliverable will arrive in week 6, but the procurement plan shows the contract award will not complete until week 8. Both plans were developed by different subteams and approved separately. What should the project manager do FIRST?
A project manager is leading a hybrid initiative with three parallel workstreams, each led by a different lead who has developed a subsidiary plan (scope, schedule, resources) somewhat independently. As the PM begins integrating these into a single project management plan, they notice the workstream plans use different assumptions about a shared testing environment and different milestone naming conventions. What should the PM do FIRST to integrate the planning activities effectively?
A project manager is leading a 12-month hybrid infrastructure project. During execution, a key regulatory change is announced that could affect several planned deliverables. The project manager notices that the risk register has not been updated since the initial planning phase three months ago, and the team continues to reference the original risk priorities. What should the project manager do FIRST?
Midway through a 14-month predictive infrastructure project, the technical lead—who holds deep undocumented knowledge of the legacy integration design—gives notice and will leave in three weeks. The project manager is concerned about continuity once this person departs. What should the project manager do FIRST to protect project continuity?
A senior integration engineer has accumulated undocumented insights about how the legacy billing system behaves under peak loads. The project will continue for another 18 months, and the engineer is highly engaged with no plans to leave. The project manager wants to ensure this valuable know-how is preserved for the broader team over time. Which approach best captures this type of knowledge?
A project is midway through execution when a functional manager verbally instructs a developer to add a small reporting feature to a deliverable, saying it is 'too minor to bother with paperwork.' The developer implements the change during the next sprint. When the project manager reviews the sprint output, the new feature is discovered. What should the project manager do FIRST?
During execution of a predictive project, a critical production defect in an already-deployed component threatens to halt the client's operations. The fix requires modifying a component that is under the project's configuration baseline. The client demands the fix be applied within hours, well before the next scheduled change control board (CCB) meeting. What should the project manager do?
Midway through the execution phase of a predictive infrastructure project, a key stakeholder emails the project manager requesting an additional feature that was not in the approved scope baseline. The stakeholder insists it is 'small' and should be added immediately to avoid delay. What should the project manager do first?
More PMP practice
Keep going with the other Project Management Professional (PMP) domains, or take a full timed mock exam.
← Back to PMP overview