Project Management Professional (PMP)150 / 152
Question 150 of 152
A project manager must roll out a new regulatory compliance process to a team of 15. Assessment shows five members are already expert in the process from a prior project, six have moderate familiarity, and four have never used it. The go-live date is fixed and near. How should the project manager ensure the team is adequately trained while using time efficiently?