Question 146 of 152
During a project retrospective, several team members mention that they frequently wait for the two most experienced engineers to review and approve their code, creating bottlenecks. The engineers are overwhelmed, and delivery is slowing. The project manager wants to strengthen overall team performance sustainably. What should the project manager do FIRST?