Project Management Professional (PMP)140 / 152
Question 140 of 152

A newly formed agile development team is unable to complete their sprint work because they lack access to a licensed testing environment controlled by a separate IT operations group. The team raises this during the daily standup, expressing frustration that they have escalated it twice with no response. As the servant-leader for the team, what should you do first?