During a hybrid project, two team members repeatedly disagree about how to sequence integration work. Instead of escalating to you, they have started bringing every disagreement to you for a decision, expecting you to pick a winner. You want the team to develop the capability to work through these disagreements themselves. As the servant-leader project manager, what is the BEST long-term approach?