During execution of a predictive infrastructure project, the project manager identifies that a specialized subcontractor has unexpectedly freed up capacity and could complete a critical work package two weeks early at no additional cost, which would let the project deliver a key milestone sooner and capture a market advantage. The PM lacks the internal expertise to guarantee this outcome alone. Which risk response strategy is the PM applying if they formally assign this work package to that subcontractor to ensure the early benefit is realized?