Project Management Professional (PMP)127 / 152
Question 127 of 152
During execution of a predictive infrastructure project, the risk owner reports that a previously identified risk—a rare regional power grid fluctuation that could corrupt data during nightly batch processing—has a low probability but would cause severe, irreversible data loss if it occurred. A backup generator and redundant storage solution would cost 8% of the remaining budget. The sponsor is cost-conscious. What is the project manager's BEST course of action?