During planning for a data-migration project, the team identifies a high-probability, high-impact threat: the legacy database format is incompatible with the new platform and could corrupt records during transfer. After analysis, the team decides to change the migration approach entirely by adopting a proven middleware tool that converts records in a supported format before transfer, eliminating the incompatibility. Which risk response strategy has the project manager applied?