Project Management Professional (PMP)125 / 152
Question 125 of 152
During execution of a predictive infrastructure project, several team members mention in casual conversations that a new government regulation may soon require additional certifications for the installed equipment. The regulation has not yet been finalized. The risk register does not currently include this item. What should the project manager do first?