Question 124 of 152

A predictive infrastructure project is entering its build phase in six weeks. The resource management plan shows that three specialized network engineers will be needed for a 10-week workstream on the critical path. The functional manager who controls these engineers informs the project manager that, due to security clearance and onboarding procedures, any assigned engineer requires four weeks of lead time before they can begin billable work. What should the project manager do FIRST?