A project manager is administering a fixed-price contract with a supplier for a specialized subsystem. During routine procurement administration, the PM notices the vendor has submitted an invoice for a milestone payment, but the corresponding deliverable acceptance record in the project artifacts shows the milestone has not yet been formally accepted by the technical team. What should the PM do FIRST?