Project Management Professional (PMP)115 / 152
Question 115 of 152
A project manager is finalizing a statement of work with an external vendor who will deliver a critical software module. During negotiations, the vendor pushes for fixed monthly payments regardless of milestones, while the project sponsor insists that payments be tied to accepted deliverables to protect the budget. Both sides are becoming entrenched, and the project cannot start until an agreement is signed. What should the project manager do FIRST to move the negotiation forward?