Project Management Professional (PMP)114 / 152
Question 114 of 152
Your project depends on a shared deliverable that a partner organization has agreed to co-develop. During early discussions, both sides express general enthusiasm but never document specifics about quality standards, delivery dates, or who owns integration testing. Three weeks in, the partner delivers an incomplete component and claims it was never their responsibility. What should the project manager have done to prevent this situation?