Project Management Professional (PMP)113 / 152
Question 113 of 152

You are initiating a new project and meeting with the sponsor to establish the project charter. During the discussion, the sponsor verbally describes an ambitious set of deliverables but is vague about budget limits and the authority you will have to make day-to-day decisions. You are concerned that these ambiguities could cause disputes later. What is the BEST action to take before finalizing the agreement?