Question 112 of 152

A project manager in a matrix organization needs three specialized engineers for an upcoming eight-week phase. Two functional managers, who control these engineers, have already committed the same resources to other initiatives and are each pushing back on releasing them. The project sponsor expects the phase to start on schedule. What should the project manager do FIRST to reach a workable resource agreement?