Question 111 of 152
Two projects in your organization both require the same database specialist during overlapping weeks. You are one of the two project managers, and neither of you has formal authority over the other. Both projects are important to the organization, and delaying the specialist's work would create risk for both. What is the BEST first step to reach a workable agreement?