Project Management Professional (PMP)110 / 152
Question 110 of 152

During a kickoff, the sponsor commits the team to a delivery date in front of senior executives without first consulting the project manager. The PM's capacity analysis shows the committed date is unachievable with the current team and scope. The sponsor is a strong personality who values decisiveness. What should the PM do FIRST?