During project initiation, two sub-teams that must collaborate daily disagree on which shared collaboration platform to adopt. Each team strongly prefers the tool they already use and has escalated the standoff to the project manager. The disagreement is beginning to delay early coordination. What should the project manager do FIRST to reach a workable agreement?