A key subject-matter expert (SME) is shared across your project and two other initiatives. The SME's functional manager verbally agreed to allocate her 50% to your project, but lately she has been pulled into the other initiatives, causing your critical activities to slip. The other project managers claim they also have priority. What should you do FIRST to secure the SME's availability?