🔥 3-day streak
Project Management Professional (PMP)99 / 152
Question 99 of 152
During execution of a predictive project, the project manager reviews a completed deliverable and notices the development team added several extra features that were not part of the approved requirements. The team explains they included the features because they believed the customer would appreciate them. The features passed internal testing and did not delay the schedule. What should the project manager do FIRST?
Reviewed for accuracy · Report an issueNext question