Midway through an agile project, the product owner notices that many user stories near the top of the product backlog are large, vaguely defined, and lack acceptance criteria. During the next sprint planning, the team struggles to commit to work because the stories are not ready. What should the project manager (serving as an agile coach) encourage the team to do to address this situation?