Project Management Professional (PMP)97 / 152
Question 97 of 152
Midway through a predictive infrastructure project, the project manager reviews the schedule and notices that a senior network engineer is assigned to three parallel critical-path tasks during the same two-week window, exceeding her available hours. The overall project deadline has some flexibility, but stakeholders expect efficient use of resources. What should the project manager do first?