A predictive infrastructure project has a sponsor who demands a committed delivery date. The schedule has three parallel paths with high estimating uncertainty, and the sponsor wants to understand the likelihood of finishing by the requested date. The project manager wants to provide a defensible completion-date range rather than a single deterministic figure. Which analysis technique should the project manager use?