A project manager is leading a predictive infrastructure project. Midway through execution, the sponsor asks for a reliable way to see whether the project will finish on the approved baseline date. The PM has been collecting actual start and finish dates for completed activities but has not yet compared them against any reference. What should the PM do FIRST to give the sponsor an accurate schedule status?