A project manager has finalized the scope statement, WBS, activity list, and network diagram for a predictive infrastructure project. The team has agreed on activity durations and cost estimates, and the sponsor has approved the funding. Before beginning execution, what MUST the project manager do to enable proper performance measurement during the project?