Question 93 of 152
Midway through a predictive infrastructure project, the project manager reviews performance data and finds a Schedule Variance (SV) of -$40,000 and a Schedule Performance Index (SPI) of 0.85, while the Cost Performance Index (CPI) is 1.02. The sponsor wants the project completed on the original finish date. What should the project manager do FIRST?