A predictive construction project is running two weeks behind on the critical path. The sponsor insists the original deadline be met, and there is a small unallocated budget reserve. The delayed activities involve pouring and curing concrete foundations, which have fixed technical durations that cannot be overlapped with the framing that follows. The project manager needs to recover schedule. Which action is most appropriate?