An agile team has completed six sprints on a product with a fixed release date three months away. Historical velocity has stabilized at 32 story points per two-week sprint. The product owner presents a prioritized backlog totaling 240 remaining story points and asks the project manager whether all of it can be delivered by the release date. What should the project manager do first?