A mid-size predictive project has an established governance structure with a steering committee that meets monthly. Midway through execution, the project manager discovers that a key regulatory deliverable will not meet a legally mandated deadline unless additional funding is approved within two weeks. The next steering committee meeting is three weeks away. What should the project manager do first?