A predictive project has delivered all planned deliverables, and the customer has begun using the product in production. The project manager wants to formally close the project. During the closure process, the PM discovers that the customer has not yet provided written sign-off on two of the final deliverables, though they are being actively used. What should the PM do FIRST?