Project Management Professional (PMP)76 / 152
Question 76 of 152

A project manager is overseeing a fixed-price contract with a vendor delivering a critical software module. During acceptance testing, the delivered module meets the functional specifications listed in the statement of work (SOW) but fails to meet an implied performance benchmark that the project team assumed but never documented. The vendor insists they have fulfilled the contract. What should the project manager do FIRST?