A project manager is overseeing a fixed-price contract with an external supplier delivering a hardware subsystem across three milestones. Midway through the engagement, the sponsor asks the PM how the vendor's actual delivery and quality performance compares to what was agreed. The PM wants a formal artifact to support an objective, documented answer. Which document should the PM rely on?