Project Management Professional (PMP)72 / 152
Question 72 of 152
A project manager is preparing to contract a specialized software integration effort. The technical requirements are not fully defined, and the team expects the scope to evolve significantly as discovery work proceeds. The sponsor is concerned about controlling total cost but also wants to avoid disputes with the vendor over changes. Which contract type is MOST appropriate for this situation?