Project Management Professional (PMP)70 / 152
Question 70 of 152
A large predictive infrastructure project has completed its design phase. Before the team begins the construction phase, the sponsor asks the project manager to confirm the project is ready to proceed and that continued investment remains justified. Several design deliverables were accepted, but two remain in rework. What should the project manager do to properly manage this phase transition?
Reviewed for accuracy · Report an issueNext question