Project Management Professional (PMP)64 / 152
Question 64 of 152
During integration testing, the QA lead insists on running a full regression suite that will take four days, while the development lead argues there is only time for a two-day targeted test before a hard release date. Both approaches have merit, and neither party will fully concede. The project manager needs a workable path forward that keeps the release date intact. Which conflict resolution approach is the project manager applying if they facilitate an agreement to run a two-and-a-half-day risk-based test covering the highest-priority modules?