Question 63 of 152
During a critical phase of a software project, the QA lead and the development lead are in disagreement. QA insists on a full regression cycle before release, while development argues this will miss the committed launch date. Both are firm, and both have valid concerns about quality and schedule. As the project manager, which conflict resolution approach is most appropriate to reach a durable outcome that both can commit to?