A predictive infrastructure project is nearing completion. The sponsor asks you to ensure that the operations team who will inherit the system can maintain it without depending on your project team, which will disband immediately after closure. Several key configuration decisions and troubleshooting workarounds currently exist only in the heads of two senior engineers. What should you do FIRST to ensure project continuity?