During execution of a predictive project, a critical production defect in an already-deployed component threatens to halt the client's operations. The fix requires modifying a component that is under the project's configuration baseline. The client demands the fix be applied within hours, well before the next scheduled change control board (CCB) meeting. What should the project manager do?