A project is midway through execution when a functional manager verbally instructs a developer to add a small reporting feature to a deliverable, saying it is 'too minor to bother with paperwork.' The developer implements the change during the next sprint. When the project manager reviews the sprint output, the new feature is discovered. What should the project manager do FIRST?