Question 51 of 152

On a hybrid software project, one developer consistently delivers the highest volume of work and meets every deadline. However, several team members privately tell the project manager that this developer dismisses their ideas in meetings, interrupts them, and takes sole credit for shared work. Team collaboration and morale are beginning to decline. What should the project manager do FIRST?